Clayton Control Systems provided "Quick-Ship" services for a scheduled shut-down of Pump Station No. 60 on the Williams Trans-Continental
Natural Gas Pipeline. The Project consisted of two (2) Motor Control Centers and forty (40) control buckets. The typical six (6) week shop
build time was compressed to one (1) week and the equipment was on-site, installed, and fully functional in two (2) weeks. Clayton Control
Systems was responsible for control engineering, MCC wiring, MCC testing, and on-site MCC start-up and training.